Congo’s PICAGL has spent $37m of $150m: the slow arithmetic of farm delivery

January 19, 2021
Women carrying cassava cuttings across a terraced South Kivu hillside beside an unfinished rice store.

Cassava cuttings and training moved first; the remaining $113m now has to deliver harder assets.

Two years into implementation, the World Bank’s $150m Democratic Republic of Congo component of the Great Lakes Integrated Agriculture Development Project (PICAGL) has disbursed about $37m, roughly a quarter of the envelope. The World Bank statement of 19 January counts 74,000 households given improved cassava planting material and more than 14,000 farmers trained in rice intensification and soil-fertility systems.

A quarter spent is not a verdict, it is a profile. Money in a project of this kind follows the work, and the work that moves first is the cheap, soft kind: cuttings, training, demonstration plots. The statement says delays came from administrative procedures, security constraints and COVID-19, and that infrastructure in the volatile east took the hardest hit. The remaining $113m therefore sits in the part of the project that is slowest to build.

What 74,000 households actually received

Planting material and training are fast outputs, and they say little yet about tonnes sold.

PICAGL works in South Kivu and Tanganyika, with Burundi as the second country. Beyond the cassava cuttings and the rice and soil-fertility courses (49 per cent of those trained were women), more than 9,000 households were trained in livestock health, 90 per cent of them young people. Each of those is a count of access, not a count of marketed produce. A cutting planted in 2020 needs months of growth before the first harvest, and only a harvest that finds a buyer becomes household income.

Why disbursement trails delivery

The Bank pays against procured goods, works and services, so a quarter disbursed means three-quarters still to contract.

The arithmetic is plain: $37m of $150m is 24.7 per cent. Bank-financed investment projects release money as goods are bought, works are certified and services are delivered, so the disbursement line trails the contracting line, which trails the planning line. Training courses and planting material clear that sequence in weeks. A rice store, a feeder road or a processing shed must pass design, bidding, a contractor’s mobilisation and the rainy season in provinces where security can close a site overnight. Slow disbursement here mostly reflects what is left to build, not money gone missing.

The price signal from Kinshasa’s markets

Cassava and tubers were the fastest-rising food line in the central bank’s January index.

The Banque Centrale du Congo weekly digest of 13 January tracks Kinshasa retail prices. Its group covering potatoes, cassava, other tubers and bananas rose 0.82 per cent in the week of 4 to 10 January, against 0.16 per cent for the general index. Over two weeks the group climbed from 168.98 to 171.64 on the bank’s base, a gain of 1.6 per cent. Cassava is a staple that Congolese households cannot easily replace, so rising prices with thin supply are the demand case for exactly what PICAGL is multiplying at the farm.

A smaller state budget raises the premium on funded projects

Public counterpart cash is tight, which favours projects that arrive with their own financing.

The government presented a 2021 budget of about $6.8bn, a sharp cut from the roughly $11bn first planned for 2020, as Financial Afrik reported in October, drawn up with the IMF asking for a realistic plan. Smaller public purchasing power means less money for roads and stores that agricultural projects usually need alongside them. A programme with $113m still to spend is therefore a sizeable pool of farm-sector money still to be placed in the east.

What a buyer or lender should do now

Approach the project while procurement is still open, and judge it on harvests, not cuttings.

Processors, millers and input suppliers working in South Kivu and Tanganyika should ask the project’s coordination unit which packages remain unawarded and when, because three-quarters of the budget has not yet been contracted into assets. Lenders should read the 25 per cent figure as a starting line and track the next disbursement milestone against delivered capacity, not against households counted. Cassava that reaches a market at rising prices would be the first proof that the training turned into trade.


By The Kanisa Desk