Financing has run ahead of steel in 2025, and the Treasury’s own capital line shows how far.
Money has been committed to Congo’s largest infrastructure projects faster than it has been poured into them. By the end of August 2025 the World Bank had approved the first US$250 million for the Inga 3 hydropower site, DP World had finished the first dredging phase at Banana, and the state’s capital budget had spent about CDF 1.13 trillion in six months. Each is a real milestone. None is a working asset yet.
The distance between a financing signature and a quay or a turbine is where contractors lose a year, and in Congo that distance can be measured. The Banque Centrale du Congo’s weekly digest of 27 August carries the Treasury’s cumulative table, and the capital line in it is a thin slice of the cash that left the state’s accounts.
Banana: the cleanest test
Private capital, a named contractor and a dredged channel show what execution looks like when the Treasury is not the paymaster.
DP World chose Mota-Engil to build the deep-water port at Banana in March 2025, with British International Investment committing up to US$35 million to the first phase. That phase is a 600-metre quay and a yard sized for 450,000 containers a year. By early July the project’s milestones, including completion of the first dredging phase, were reviewed in a meeting between Vice Prime Minister Jean-Pierre Bemba and DP World’s Sub-Saharan Africa chief, Mohammed Akoojee, with first-phase completion targeted for early 2027.
Banana moves because the contractor is paid from a ring-fenced private facility rather than from the state’s weekly cash plan. The channel had to exist before the quay could be driven, and it does. That is the sequence a lender can verify from a survey vessel.
The Treasury’s arithmetic
Capital spending was 7.4 per cent of first-half outlays; salaries took 35.7 per cent.
The BCC’s table, built on Finance Ministry data, shows revenue of CDF 13.41 trillion and spending of CDF 15.29 trillion in the first half of 2025, a cash deficit of CDF 1.88 trillion. Of that spending, CDF 1.13 trillion went on capital projects. At roughly CDF 2,870 to the dollar that is about US$395 million, or 7.4 per cent of outlays. In 2024 as a whole, capital spending was CDF 3.54 trillion of CDF 28.94 trillion, or 12.2 per cent.
Compensation of staff took CDF 5.46 trillion, and the line labelled exceptional expenditure took CDF 4.64 trillion, 30 per cent of the total. A project that depends on the state’s own cash competes with both, and it ranks behind them.
For scale, the Inga 3 first tranche alone equals roughly 63 per cent of everything the state recorded as capital spending in the half-year.
Inga 3: an approval starts a clock
A US$250 million first tranche opens a process of resettlement, procurement and permitting; it does not start a turbine.
The World Bank approved that initial US$250 million on 3 June, according to Mongabay’s report, which puts the scheme’s output at between 4,800 and 11,000 megawatts. The same report records objections from International Rivers, which says the project could displace more than 30,000 people, and from campaigners who argue the power would serve exporters and mining customers rather than the roughly 80 per cent of Congolese without electricity. It also notes that the Bank had earlier suspended funding over concerns about the developer’s political independence.
None of this is unusual for a project of this size, but it sets the order of work. Compensation of people already moved by Inga 1 and 2 has to be settled, a developer has to be procured, and only then does the civil-works contractor mobilise.
What the checkpoint tests
Price the schedule by the stage a project has reached, not the amount announced.
Suppliers and contractors should sort every Congolese infrastructure announcement onto a ladder: proposed, approved, financed, contracted, under construction. Banana sits on the later rungs, with a contractor on site and a channel dredged. Inga 3 sits on the second.
The practical rule follows from the BCC’s table. Where the paymaster is a development lender or a port operator, build the order book now. Where it is the Treasury, assume payment follows salaries and exceptional items, and insist on escrowed or lender-backed payment terms. The next digests will show whether the capital line moves from 7 per cent of outlays toward last year’s 12.
Sources
- Banque Centrale du Congo – Condensé hebdomadaire d'informations statistiques (27 August 2025)
https://www.bcc.cd/statistiques/condense-informations-statistiques/2025-08-27 - Maritime Executive – DRC's Banana Port Achieves Construction Milestone (March 2025)
https://maritime-executive.com/article/drc-s-banana-port-achieves-construction-milestone - Dredging Today – Banana Port development moves ahead, spotlight on dredging (4 July 2025)
https://www.dredgingtoday.com/2025/07/04/banana-port-development-moves-ahead-spotlight-on-dredging/ - Mongabay – World Bank to finance controversial DRC hydropower project, concerns remain (June 2025)
https://news.mongabay.com/short-article/2025/06/world-bank-to-finance-controversial-drc-hydropower-project-concerns-remain/