By July 2025 the DRC’s infrastructure bottleneck sat between financing decisions and the cash actually spent.
On 3 June 2025 the World Bank’s board approved a US$250 million IDA credit, the first phase of a US$1 billion Inga 3 Development Program. By the IMF’s count, only 25 per cent of the 2025 investment budget had been executed by the end of May. The distance between those two facts is the story of Congolese infrastructure in July.
Approved money is one rung of a ladder that runs from proposed to approved, financed, contracted, under construction, commissioning and operational. Inga 3 has reached the second rung, and in the form of community works rather than a dam. The Treasury’s own spending lines show why the rungs above are slow to climb.
What the money buys
The first Inga 3 tranche builds water points, rural roads and skills, not turbines.
According to the World Bank’s announcement, the credit will serve around 100 communities, about 1.2 million people in Kongo Central, with water, distributed renewable energy, rural roads, training and technical studies. The Agency for the Development and Promotion of Grand Inga, ADPI-DRC, is the implementer, and its head Bob Mabiala says technical and governance foundations and community support will be essential.
The programme is designed to run for roughly a decade. Only 21 per cent of Congolese have electricity, against a national target of 62 per cent by 2030, so the generation prize is large. That prize sits on later rungs, and the Bank describes the site’s potential as 2 to 11 gigawatts. Selecting dam sponsors, financing the plant and signing grid and offtake contracts are separate steps, and this credit covers none of them. A reader tracking Inga 3 should therefore count community works completed, not megawatts promised, as the measure for 2025.
The Treasury’s own execution line
Capital spending was 7.4 per cent of outlays at the end of June, while exceptional spending took 30 per cent.
The BCC’s digest of 30 July carries the Treasury’s cumulative accounts to 27 June. Capital expenditure was CDF 1,134.8 billion out of total expenditure of CDF 15,293 billion, which is 7.4 per cent, against 12.2 per cent for 2024 as a whole. Compared with the first half of 2024, capital spending rose 8 per cent while total spending rose 28 per cent. Exceptional expenditure, which includes the security response, reached CDF 4,643 billion, nearly a third of all outlays.
The July columns in that table are copies of June, flagged as data not available, so the picture ends at the half-year.
Why execution lags approval
Late project design, emergency spending and security demands crowd out capital works.
The IMF’s staff report gives three reasons. Projects under the SICOMINES agreement, the Sino-Congolese joint-venture arrangement that funds roads and other works, were budgeted at 0.4 per cent of GDP in 2024 and delivered 0.1 per cent, because the authorities finished designing them late in the year. Emergency procedures took 15.6 per cent of total spending in the first quarter of 2025, against a ceiling of 8 per cent for the end of the year, driven by security costs. And the programme names investment projects that could be delayed if fiscal pressure grows.
The IMF says the authorities will accelerate SICOMINES projects as an offset. A government and SICOMINES memorandum on the mechanism was to be adopted within weeks, and budget support meant for investment will go to a BCC sub-account.
What a contractor or lender does next
Follow the cash mechanism, not the announcement, and price payment delay into every bid.
A contractor reading the Inga 3 approval should look to ADPI-DRC’s procurement notices and expect small packages: wells, solar kits, rural roads and training. They are worth winning because they come with World Bank procurement rules and a donor payer rather than the Treasury. A supplier bidding for Treasury-financed work should assume late payment: in 2024 about 70 per cent of capital spending was booked after June, and arrears followed.
The lender’s equivalent is to ask where a project sits on the ladder and whether its payer sits inside or outside the Treasury. The next test is the amended budget law, which will show whether the government protects capital works or cuts them first.
Sources
- Banque Centrale du Congo – Condensé hebdomadaire d'informations statistiques n°30 (30 July 2025)
https://www.bcc.cd/statistiques/condense-informations-statistiques/2025-07-30 - Banque Centrale du Congo – Notes de conjoncture
https://www.bcc.cd/publications/notes-de-conjoncture - World Bank – New Inga 3 Development Program to Start with Investments in Local Congolese Communities (3 June 2025)
https://www.worldbank.org/en/news/press-release/2025/06/03/new-inga-3-development-program-to-start-with-investments-in-local-afe-congolese-communities - IMF – Democratic Republic of Congo: First Review under the Extended Credit Facility Arrangement, Country Report No. 25/195 (July 2025)
https://www.imf.org/-/media/files/publications/cr/2025/english/1codea2025002-source-pdf.pdf