Three Kongo Central megaprojects, three rungs: Inga, Banana and the road between

June 30, 2025
Surveyors and a drill rig on cleared ground near the Atlantic coast, with an empty road corridor behind

Capital spending has run behind the calendar while headline projects sit at different stages.

Finance is moving faster than concrete in Kongo Central, and the BCC’s own budget table shows it. By 21 May 2025 the Treasury had spent CDF 1,039 billion on capital projects, about US$363 million and 29 per cent of the whole of 2024’s capital spending, with 38 per cent of the year gone. Meanwhile, three headline projects in the same province, Inga 3, the Banana port and the Kinshasa-Banana road, sit on three different rungs of the ladder from proposal to operation. Money in a press release is a start, not a structure.

Reading the three side by side shows where the delay in delivery is likely to occur.

Inga 3: financed for preparation, not for construction

The first dollars go to the villages and the studies, which is where the permits and the licence to operate come from.

On 3 June the World Bank approved a US$250 million IDA credit as the first phase of a US$1 billion Inga 3 Development Program. The money funds clean water, distributed renewable energy and rural roads for about 100 communities with 1.2 million people, plus skills training, technical studies and preparation work. The Bank said the plant could produce between 2 and 11 gigawatts and take around a decade to build, and that only 21 per cent of Congolese have electricity, against a 62 per cent target for 2030.

The project was also described by trade press on 10 June as the largest energy initiative ever attempted in the DRC, with the government aiming under its National Energy Pact to lift electricity access to 62 per cent by 2030. On the ladder, though, that is Financed for preparation. It is not Contracted, nor Under Construction, and the ten-year build is still a long way off.

Banana: a builder has been named

A private operator with a funder and a contractor has moved furthest, but only for the first phase.

A Kuehne+Nagel bulletin of 27 March reported that DP World would build the Banana port with Mota-Engil, the Portuguese contractor, and described it as a complement to Matadi and Boma rather than a replacement. Phase one would include a 600-metre quay, 30 hectares of storage and capacity of 450,000 containers a year, with a second phase extending the quay wall by more than two kilometres. The bulletin did not state an investment figure or a timetable.

That sits at Contracted. The risk is not the quay but what connects it. A deep-water berth is useful only if cargo can leave in volume.

The road to Banana is still a signature

An agreement without a budget, a route or a date is a proposal.

On 20 May the government signed an agreement with the Chinese firm Zhongshi Wozen Technology for a highway of about 450 kilometres linking Kinshasa to Banana, according to Ecofin. The agency noted that no budget or timeline had been published, that the exact route was still to be fixed, and that funding, execution conditions and security on the corridor could be obstacles.

On the ladder, that is Proposed. It is the weakest of the three links, and the port’s value depends on it.

Why execution lags finance

Procurement, preparation and payment each add months that a financing announcement does not show.

The mechanism has three steps. Financing is a commitment that a lender will pay against delivered work. Procurement then selects a builder, and preparation secures land, resettlement and permits. Only then does money flow against works, and the Treasury’s capital line moves. The BCC’s table shows the last step is the slow one: capital outlays have run below the calendar even though revenue has run ahead of it.

For a builder or supplier, the implication is that the pipeline looks fuller than the work programme.

What to do

Bid on what is contracted, prepare for what is financed, and ignore what is only signed.

Contractors, equipment lessors and cement suppliers should plan to the rungs. Banana phase one is the nearest work, so suppliers for quay, storage and haulage should position now. Inga’s community programme is the next, with water, rural roads and training contracts. The highway should be treated as a possibility until a route, a financier and a budget are named. The test of progress is simple: look for the tender notice, not the signing photograph.


By The Kanisa Desk